Water Neutrality in Sussex North Has Ended: What Natural England Changed and What Replaces It

TL;DR: On 31 October 2025 Natural England withdrew its September 2021 position statement, which had required new development in the Sussex North Water Supply Zone to be water neutral to protect the Arun Valley habitats. The change rests on the water company’s Hardham study and an agreed package: cutting the Hardham licence from 16.44 to 13 megalitres a day on average and the daily peak from 30 to 27, plus measures at Pulborough Brooks, to be implemented by March 2026. Councils are now moving to water efficiency conditions such as the 110 litres per person per day optional standard, and the area remains water stressed.

Last updated: 27 October 2026

Key takeaways

  • Water neutrality Sussex North began with a Natural England position statement in September 2021 advising that new development in the Sussex North Water Supply Zone should demonstrate water neutrality, to protect the Arun Valley habitats from the water company’s groundwater abstraction at Pulborough.
  • On 31 October 2025 Natural England withdrew that statement, after the water company’s Hardham Basin Environmental Study and an agreed package of measures.
  • The package cuts the Hardham abstraction licence from 16.44 to 13 megalitres a day on average, which is 6,000 to 4,745 megalitres a year, and the daily peak from 30 to 27 megalitres, with ecological measures at Pulborough Brooks, all to be implemented by March 2026.
  • Natural England advised that local authorities do not need to undertake an appropriate assessment or consult it on water scarcity issues affecting the Arun Valley sites for these applications.
  • Councils are moving from neutrality to water efficiency, with planning conditions such as the Part G optional technical standard of 110 litres per person per day replacing the stricter local figures used before.
  • Natural England describes the area as still water stressed, so efficient design, metering and leak control still matter.
Water neutrality Sussex North in numbers: withdrawn on 31 October 2025, Hardham licence cut to 13 megalitres a day on average and 4,745 megalitres a year, measures to be in place by March 2026
The rule ended, and the abstraction was capped instead.

For four years, a housebuilder in Horsham, Crawley or the northern part of Chichester district had to prove that a new home would use no more water than the area did before. Schemes were held for years, planning conditions capped use at 85 litres per person per day, and a whole offsetting industry grew up around retrofitting taps and toilets in existing homes.

On 31 October 2025 that requirement was withdrawn. This guide explains what water neutrality Sussex North was, what Natural England changed and why, what the agreed package contains, what replaces neutrality in planning, and what developers and designers should check now. It draws on Natural England’s own withdrawal statement.

What was water neutrality Sussex North all about?

Water neutrality Sussex North was an interim planning approach that required new development in the Sussex North Water Supply Zone to demonstrate no net increase in water use. It followed a Natural England position statement of September 2021, which said abstraction within the zone could not be ruled out as having an adverse effect on the integrity of the Arun Valley designated sites.

According to Natural England’s withdrawal statement, the 2021 statement advised that new development should demonstrate water neutrality to protect the Arun Valley habitats from potential impacts linked to the water company’s groundwater abstraction at Pulborough. The sites are the Arun Valley Special Area of Conservation, the Arun Valley Ramsar Site and the Arun Valley Special Protection Areas.

The approach was interim because the water company was completing an environmental study, and it applied while that study was carried out. In practice, developers met it by designing for very low water use, adding rainwater harvesting and greywater systems, and paying for or delivering offsetting in existing buildings.

What did Natural England change on 31 October 2025?

Natural England withdrew its September 2021 position statement. It advised that new development supplied by groundwater abstraction at Pulborough is not likely to have a significant effect on the Arun Valley sites, because of the findings of the water company’s Hardham Basin Environmental Study and the measures agreed by the water company and the Environment Agency.

The statement says the study was completed in August 2025 and reviewed by Natural England’s specialists in freshwater systems, hydrogeology, invertebrates, ornithology and plants. It found limited or no hydrological connection between the abstraction and two of the three constituent sites, Waltham Brooks and Amberley Wild Brooks, though some connectivity could not be ruled out at Pulborough Brooks.

Natural England says limiting the Hardham licence decouples the abstraction from new development, which prevents additional pressure on Arun Valley water resources. It also advises that local authorities do not need to undertake an appropriate assessment or consult Natural England on water scarcity issues affecting the sites for applications in the zone.

What is in the agreed package?

The package has four parts: a reduction in the Hardham abstraction licence, on-site water level management at Pulborough Brooks, monitoring of the sites, and ecological resilience measures. The licence is cut from 16.44 to 13 megalitres a day on average, and the daily peak from 30 to 27 megalitres. The measures are to be implemented by March 2026.

The Hardham abstraction licence change: annual quantity cut from 6,000 to 4,745 megalitres, average from 16.44 to 13 megalitres a day, and daily peak from 30 to 27 megalitres a day
The licence is capped at about what was recently abstracted.

The statement sets out the details:

  • Licence cut. The annual quantity falls from 16.44 megalitres a day, or 6,000 megalitres a year, to 13 megalitres a day, or 4,745 megalitres a year. The daily peak falls from 30 to 27 megalitres. The cap reflects actual recent historical abstraction and removes additional headroom.
  • Water levels. The RSPB manages sluices at Pulborough Brooks to maintain suitable water depths and prevent further deterioration.
  • Monitoring. The water company continues to build a scientific baseline of site conditions, with hydrometric and ecological monitoring, to show the measures work.
  • Resilience measures. Actions such as reprofiling and desilting ditches and controlling invasive species.

Note the role of monitoring. The settlement depends on measuring water levels and ecology, which is the same discipline that applies to any site that must show its water behaves as designed.

Where did water neutrality Sussex North apply?

It applied to the Sussex North Water Supply Zone, the area supplied by the water company from groundwater abstraction at Pulborough, which covers most of the Horsham and Crawley districts and part of the Chichester district north of the South Downs. The South Downs National Park Authority notes that parts of the National Park fall within the zone, including parts of the Chichester, Horsham and Arun areas.

Natural England’s statement applies to new development supplied by abstraction from groundwater at Pulborough. If you are working on a site near the edge of the zone, check the supply zone with the local planning authority and the water company, because the boundary follows the water supply, not the district line.

What happens to offsetting and Section 106 obligations?

New schemes no longer need water neutrality offsetting or the associated Section 106 obligations, and the planned Sussex North Water Certification Scheme will not launch. Schemes can proceed on the basis of the water company’s 2024 to 2025 efficiency savings, from 1 November 2025, according to a planning ecology summary of the announcement.

For schemes already approved with conditions or legal obligations tied to neutrality, the position is less simple. The South Downs National Park Authority says it can begin issuing decisions on live applications held up by water neutrality, expects applications to vary existing water neutrality conditions and obligations, and says clearing the backlog and those variations will take a number of months. If you hold a consent with a neutrality condition, speak to the planning authority about varying it.

What replaces water neutrality Sussex North in planning?

Water efficiency conditions replace it. Councils are asking for new homes to meet the Part G optional technical standard, which is currently 110 litres per person per day, instead of the stricter local figures used under neutrality. Horsham has been reported as reapproving schemes with the 110 condition in place of an earlier 85 litre limit.

The planning test before and after the withdrawal: until October 2025 development had to prove no net increase in water use, often with 85 litres per person per day and offsetting, and from 1 November 2025 councils use water efficiency conditions such as 110 litres
The test moved from neutrality to efficiency.

The standard itself may tighten. Defra consulted until December 2025 on cutting the mandatory national figure to 105 and the optional one to 100. Our guide to Part G water efficiency explains the current limits, the proposal and how compliance is shown, so a scheme designed to a stricter figure now will not need rework later.

How does this compare with nutrient neutrality?

Water neutrality and nutrient neutrality are separate planning constraints that both came from the Habitats Regulations. Water neutrality in Sussex North was about the amount of water taken from the ground, and nutrient neutrality is about nitrogen and phosphorus entering protected rivers and estuaries from new development’s wastewater and runoff. The withdrawal described here does not change any nutrient neutrality requirement, which applies in other catchments with its own rules and offsetting. Our guide to nutrient neutrality monitoring explains that side.

What points about the withdrawal are easy to misunderstand?

Five points cause confusion, and each is worth stating plainly.

  1. It did not make water unlimited. Natural England says the area is still water stressed, and the new approach caps the licence and manages the site.
  2. Existing conditions do not vanish. A consent that carries a neutrality condition keeps it until the authority agrees to vary it, and the South Downs authority expects that to take a number of months.
  3. It applies to the supply zone. The advice is for development supplied by abstraction from groundwater at Pulborough, not for every site in the three districts.
  4. The licence is a reduction. The water company volunteered to cut the Hardham licence to about its recent actual abstraction, which removes headroom as well as limiting it.
  5. Efficiency still counts. Councils are asking for water efficiency conditions, so a scheme still has to show low water use, only through a different test.

Keep a copy of Natural England’s statement on the file for any scheme in the zone, because it sets out the evidence and the date from which the advice applies.

What does it mean for developers and designers?

It means faster consents, less offsetting cost and a switch from proving neutrality to meeting an efficiency standard. The planning ecology summary says the changes are expected to unlock around 4,000 stalled homes and 17,000 additional homes. For a scheme in the zone, the practical steps are about conditions, design and evidence.

  1. Check your decision notice. Look for neutrality conditions, a water use cap and Section 106 obligations, and ask the authority how it will treat them now.
  2. Design to the efficiency standard. Use the fittings approach or the calculator and aim at or below the current 110 litre figure.
  3. Keep the water-saving features if they are cheap. Rainwater harvesting and efficient fittings still lower bills and risk.
  4. Plan the evidence. Meters on each home and a handover reading give you proof of performance.
  5. Watch the licence. The revised Hardham licence is to be issued, and the position should be checked against the current Environment Agency record.
  6. Keep records. If the standard tightens, your design file and measured data are your defence.

Why does water stress still matter after the withdrawal?

Natural England itself says the area remains water stressed, so the withdrawal does not mean water is plentiful. It means the habitat concern is handled through a licence cap and site measures instead of through every new home proving neutrality. Efficient use still protects supply, lowers running costs and avoids pressure on the same source.

For a developer or a landlord in the zone, that points to the same tools as before, used more lightly: efficient fittings, rainwater storage and reuse, metering and leak detection. Our guides to rainwater harvesting for new builds, the Smart Water Butt, water sub-metering and nutrient neutrality monitoring cover them, and the water demand management guide shows how they fit together.

What to do now in the Sussex North zone: check conditions, design to the efficiency standard, plan metering, watch the licence and keep records
Six checks for any scheme in the zone.

What is still uncertain?

Three things need watching. The revised Hardham licence is to be issued, and I could not find a notice confirming that it has been. The detail of how each council writes its efficiency condition may vary. And the national standard may tighten from the current 110 litres.

Natural England’s statement sets the implementation date for the agreed measures as March 2026, so by now they should be in place, but check with the Environment Agency and the local planning authority before you rely on it for a particular site. Treat this guide as background, and check the current position before you make a commitment.

Frequently asked questions

What was water neutrality in Sussex North?

It was a planning approach, from a Natural England position statement of September 2021, requiring new development in the Sussex North Water Supply Zone to demonstrate no net increase in water use, to protect the Arun Valley habitats from groundwater abstraction at Pulborough.

Has water neutrality been withdrawn in Sussex North?

Yes. Natural England withdrew its September 2021 position statement on 31 October 2025, following the water company’s Hardham Basin Environmental Study and an agreed package of measures.

What replaced water neutrality?

Water efficiency conditions. Councils are asking for new homes to meet the Part G optional technical standard, currently 110 litres per person per day, instead of the stricter figures used under neutrality.

What is happening to the Hardham abstraction licence?

It is being reduced from 16.44 to 13 megalitres a day on average, which is 6,000 to 4,745 megalitres a year, and from 30 to 27 megalitres a day at peak, with measures at Pulborough Brooks to be implemented by March 2026.

Do I still need offsetting or a Section 106 for water neutrality?

New schemes do not, and the planned certification scheme will not launch. If you hold a consent with a neutrality condition, ask the planning authority about varying it.

Is the Sussex North area still water stressed?

Natural England says the area remains water stressed, so efficient design, metering and leak control still matter even though neutrality has ended.

Where to start

Read your decision notice, then ask the planning authority how it will treat any neutrality condition. If you want to prove your homes use what you designed, contact AQUAIOT with the number of homes and the water systems you plan, and we will suggest how to meter, detect leaks and monitor rainwater storage.